Schedule

Schedule of anticipated key milestone dates for the south portion

GWP 5151-21-00

Transportation Environmental Study Report – Advanced Clearing

Summer 2025

Advanced Clearing

Winter 2025/2026 to Spring 2026

Supplemental Natural Science Field Investigations (Species at Risk Reptiles)

Summer 2026

Design and Construction Report

Summer 2027

2+1 Mainline Construction

Summer 2028

Schedule of anticipated key milestone dates for the north portion

GWP 5033-22-00

Supplemental Natural Science Field Investigations (Species at Risk Bats and Migratory Birds)

Winter 2025/2026 to Spring 2026

Supplemental Natural Science Field Investigations (Species at Risk Reptiles)

Summer 2026

Transportation Environmental Study Report – Advanced Clearing

Winter 2026/2027

Advanced Clearing

Late Fall/Winter 2027

Design and Construction Report

Summer 2028

2+1 Mainline Construction

Summer 2029

Note: Schedule is subject to change and will be updated throughout the Project.

Timing for advanced clearing and mainline construction are subject to funding, completion of detail design and the Class EA process; and, having necessary permits, licences, approvals, and authorizations in place to perform the work, in advance of construction.

Contact List Registration

We want to hear from you! Your input is important to us. To be added to the Project Contact List or to send your comments to the Project Team, please enter your email below.

Please enter a valid email address.
Something went wrong. Please check your entries and try again.